File #: 18 - 375    Version: 1 Name:
Type: Contract/Agreement/Leases Status: Passed
File created: 10/25/2018 In control: Board of County Commissioners
On agenda: 11/20/2018 Final action: 11/20/2018
Title: Consideration of a change order to add conduit and wiring back to the main distribution panels due to the fact that the conduit runs could not be reused and new main distribution circuits need to be run overhead back to the main distribution panel.
Attachments: 1. FCI Change Order

title

Consideration of a change order to add conduit and wiring back to the main distribution panels due to the fact that the conduit runs could not be reused and new main distribution circuits need to be run overhead back to the main distribution panel.