Title:
|
Consideration of a report on the current change orders in the amount of $155,841.25 for the Archer Complex project: FCI Constructors, Inc. $79,796 for Public Works; AP Wyoming $44,131 for Juvenile Services Center; Sierra Detention $16,511 for Juvenile Services Center; Richardson Construction $6639.25 for Shooting Education Center; AP Wyoming $8,764 for utility work.
|